Amazon is spending billions of dollars on NVIDIA AI systems, but some devices still cannot be powered on.
Businessinsider
1h ago
Ai Focus
According to an internal email cited by Business Insider, under the new Early Rack Receipt process, AWS is expected to receive approximately $5 billion worth of NVIDIA GB300 server racks at its facilities in the United States before the final deployment, and an additional $3 billion worth of racks will be received each month for the coming months. Due to insufficient power supply at some data centers, the completed equipment is temporarily stored in transit warehouses, which Amazon describes as a standard practice.
Helpful
No.Help

Amazon is accelerating the early locking of AI hardware, even though power shortages in data centers mean that some GPU systems will still have to wait in warehouses.

According to an internal email from August viewed by Business Insider, under a new “Early Rack Receipt” process, AWS is expected to receive approximately $5 billion worth of NVIDIA GB300 server racks before the final deployment in its US facilities. The email also states that the company anticipates receiving another $3 billion worth of GB300 racks each month for the “foreseeable future.”

People familiar with this arrangement stated that although some sites of AWS still have space to accommodate more racks, there is a shortage of available power, which prevents them from being put into use. As a result, the completed equipment will be temporarily stored in a transit warehouse until the facilities are ready to accommodate it.

One of the emails stated that at least one AWS team did not have a “clear, predictable path” to deliver the newly arrived racks into the data center at that time.

Dark GPU

Insufficient additional power capacity is one of the multiple bottlenecks that are slowing down the construction of some AI data centers. This has given rise to what is known as the "dark GPU" phenomenon, where AI chips and servers have been purchased but cannot be put into use due to power supply issues or other challenges. ("Dark GPU" can also refer to system design flaws that prevent these devices from being fully utilized even when powered on.)

This is also one of the reasons why large data center projects face financial pressures. Enterprises must invest funds in the early stages to secure the supply of NVIDIA GPU and other high-value AI components. However, if some data centers are not yet ready to operate, these early investments will tie up a large amount of cash. Debt financing can fill the gap, but recently, the market's willingness to lend against these projects as collateral has weakened.

Trade-offs

Amazon's early rack projects were part of this cloud computing giant's broader AI construction plan, which is now putting new pressure on its cash flow, as Business Insider reported exclusively this week. Amazon expects its capital expenditures this year to be around $220 billion, exceeding any of its large tech peers. Its free cash flow turned negative for the first time since 2023 in the previous quarter, and this situation may continue for some time to come.

For AWS, the trade-off is as follows: to secure the scarce GPU racks before competitors can, even though some data centers are not yet ready to put them into use. However, taking control earlier also means that billions of dollars will be invested in hardware before these devices start generating cloud revenue.

Previously, according to internal documents, AWS only took ownership of the completed racks once they were delivered to the data center. Under the new approach, the company can make payments for certain racks and record them in the accounts at an earlier stage of the supply chain.

An Amazon spokesperson stated that the company typically keeps the completed hardware near the deployment sites so that it can be installed immediately when production capacity becomes available, calling this "best business practice." The spokesperson also added that Amazon has had a well-established infrastructure asset tracking system for a long time and denied that the company generally lacks pathways to transport racks into data centers.

Amazon CEO Andy Jassy previously stated that the company "sees very clearly" the high returns on investment in AI, calling this technology a "once-in-a-lifetime opportunity."

Tip
$0
Like
0
Save
0
Views 22
CoinMeta reminds readers to view blockchain rationally, stay aware of risks, and beware of virtual token issuance and speculation. All content on this site represents market information or related viewpoints only and does not constitute any form of investment advice. If you find sensitive content, please click“Report”,and we will handle it promptly。
Submit
Comment 0
Hot
Latest
No comments yet. Be the first!
Related
Swiss regulatory authorities approve first retail fund that directly holds Bitcoin
Swiss Financial Market Supervisory Authority FINMA Approves the Country's First Retail Fund That Directly Holds Bitcoin, Exempting It from Risk Diversification Rules; The Agency Has Not Disclosed the Name of the Fund or Its Issuer.
Decrypt
·2026-10-21 04:01:38
5
UnitedHealthcare and Humana will terminate the Medicare Advantage program for nearly 1 million people
Medicare Advantage plans to continue contracting in 2027. Industry insiders say that insurance companies are responding to rising utilization rates and medical costs by increasing out-of-pocket expenses, shrinking their networks, and cutting supplementary benefits. UnitedHealthcare and Humana will affect approximately 390,000 and 600,000 people respectively.
Fortune
·2026-10-21 04:01:36
7
CSU Truck Drivers' Union to Hold a Rally Demanding that the School Authorities Respect the Contract
Teamsters Local indicates that its members will hold a rally in San Diego on October 21st to support thousands of employees of the California State University system, and to call on the university administration to fulfill their contractual obligations, including paying the salary increases guaranteed by the contract.
PR Newswire
·2026-10-21 03:51:52
9
General Motors to close battery assembly plant near Detroit, but the reason is not due to adjustments in its electric vehicle strategy
A General Motors spokesperson confirmed to TechCrunch that the company will close its Browns敦 battery assembly plant located south of Detroit. The company stated that this move is not related to its electric vehicle strategy, but mainly due to the upcoming expiration of the lease for the site; the relevant employees and work will be transferred to other General Motors facilities.
TechCrunch
·2026-10-21 03:41:36
17
Dental experts Ryan Smith and Scott Wilkes analyze the differences between dental implants and partial dentures
An article with the ID HelloNation introduces the views of dental experts Ryan Smith and Scott Wilkes from Rexburg, Idaho. It compares the differences between dental implants and partial dentures in terms of stability, treatment time, cost, maintenance, and suitability, to help patients make informed choices regarding tooth replacement options.
PR Newswire
·2026-10-21 03:10:42
17
View More