Bitcoin mining company CleanSpark indicates that the company may sell more bitcoins than it mines itself in order to reduce its exposure to fluctuations in the cryptocurrency market, and to fund expansion without relying excessively on new debt or equity financing.
The key points are as follows:
- CleanSpark is considering selling more Bitcoin than the amount mined to reduce inventory exposure.
- The company sold or delivered 2,102 units of BTC, while the quarterly production was 1,708 units of BTC.
- This Bitcoin mining company reported an annual net loss of $987.1 million, with revenue declining by 25%.
- As of the end of September, CleanSpark held 13,530 BTC and $204.8 million in cash.
- The company's goal is to deliver its first AI data center located in its campus in Georgia by November 2027.
At the company's financial report conference call on November 24th, Chairman and Chief Financial Officer Gary Vecchiarelli stated that CleanSpark originally intended to sell almost all of the newly mined bitcoins to cover operating expenses.
Management is still considering further utilizing the existing reserves when market conditions and capital needs warrant it.
According to the latest financial disclosures, CleanSpark held 13,530 units of BTC at the end of the fiscal year on September 30, which included Bitcoin used as collateral.
CleanSpark considers further selling its bitcoin inventory
In answering analysts' questions regarding the company's inventory management strategy, Vecchiarelli stated that moderately selling off Bitcoin that exceeds quarterly production could help to reduce financial risks.
He explained that future sales will depend on market conditions and the company's financing needs, especially in cases where CleanSpark wishes to avoid raising funds for expansion through additional share issues or taking on unnecessary debt.
In the past quarter, this mining company has reduced its Bitcoin reserves. As crypto.news reported on November 10th, CleanSpark sold or delivered 2,102 BTC between July and September, while the production during the same period was 1,708 BTC.
The difference between the two is 394 BTC, which accounts for about 23% of the company's quarterly mining output.
CleanSpark produced 586 BTC in July, 593 BTC in August, and 529 BTC in September. During the same period, the sales and delivery volumes of Bitcoin were 579, 821, and 702 units respectively.
Not all transactions involve direct selling on cryptocurrency exchanges. For example, in September, CleanSpark only sold 2 units of BTC in the spot market, while another 700 units of BTC were delivered by exercising a call option.
As of the end of September, 3,475 BTC bitcoins from the company's remaining bitcoin holdings have been pledged as collateral or recorded as receivables related to derivative transactions.
CleanSpark recorded an annual loss of $987 million amid declining revenue
According to the financial report released on November 24th, CleanSpark incurred a net loss of $987.1 million in the fiscal year 2026, whereas the net profit in the previous fiscal year was $364.5 million.
Management stated that about two-thirds of the difference in performance over the two years came from non-cash adjustments due to changes in the value of Bitcoin holdings.
Annual revenue decreased by 25% to $576.5 million; adjusted earnings before interest, taxes, depreciation, and amortization (EBITDA) resulted in a loss of $304.2 million.
The company's performance in the fourth fiscal quarter was different. Although quarterly revenue decreased by 46% to $120.9 million year-on-year, CleanSpark still recorded a net profit of $9.8 million, equivalent to a basic earnings per share of $0.04.
In August, this mining company announced a quarterly net loss of $239 million and revenue of $138 million.
As of the end of September, CleanSpark held approximately $204.8 million in cash and cash equivalents, as well as a Bitcoin position of $1.13 billion. The total liquidity, calculated at the end of the year, was about $1.3 billion, which includes pledged assets.
CleanSpark Reducing the scale of mining machines leads to a decrease in production
In the fiscal year 2026, CleanSpark mined 7,253 BTC, a decrease of 8% compared to the previous year; the average computing power also decreased by 21%, to 36 EH /s.
Despite the decrease in production, the company has improved the efficiency of its mining equipment. By the end of September, the energy consumption of its mining machine fleet was 14.8 joules per terahash, compared to 16.7 joules at the end of the fiscal year 2025.
Vecchiarelli stated during the financial report conference call that as long as operations remain profitable, the company intends to continue mining Bitcoin, with the computing power fluctuating according to business conditions.
The company obtained $30.6 million in revenue from derivative transactions this fiscal year through its digital asset management plan.
CleanSpark Previously announced that it would stop releasing mining updates on a monthly basis. As the business expands beyond cryptocurrency mining, it has decided to disclose operational data on a quarterly basis instead.
CleanSpark Advances $6.6 Billion AI Data Center Project
Meanwhile, the construction of CleanSpark in the Sandersville campus in Georgia is still progressing as planned, with the company aiming to deliver the first artificial intelligence data center by November 2027.
The project is supported by a 20-year lease agreement, and the lessee is an investment-grade client. CleanSpark is expected to generate approximately $6.6 billion in contract revenue.
Following a previous secured debt arrangement, the company raised $2.276 billion through senior secured notes with an annual interest rate of 7.875%, maturing in 2031.
Vecchiarelli indicates that: 'The completion of the financing by Sandersville has provided dedicated capital for the project, and full funding has already been secured for the project.'
Outside of Georgia, CleanSpark has obtained conditional base load power capacity of 585 megawatts for its properties in Sealy and Brazoria in Texas.
At the property in Washington in Georgia, the company has acquired an adjacent 500 acres of land for a potential AI data center campus, and has submitted a transmission study to expand the available power capacity from 86 megawatts to a maximum of 500 megawatts.